2014-02-14 - 11375 - Break Fix - Investigate planning time fence lot size #ProductionBreakFix #mrpexecution

2014-02-14 - 11375 - Break Fix - Investigate planning time fence lot size

Problem Summary


Investigate planning time fence lot size

Admin Info


Purpose
Investigate planning time fence lot size
Requested by
Babu Lankipalli
Issue Date
02-14-2014
Resolved by
Laxman
Resolved Date
02-17-2014
Document Status
Complete

Detailed Problem Description

(Include Screen Shots if required )

Purchase reqs are not batching due lot size, We have to maintain Z1 (9months) planning in material master and Z1 is expecting factory calendar for the year 2016.
May need to update factory calendar to 2016.

Solution Analysis and Recommendations

(Include Screen Shots if required)

It was observed that While running the mrp if lot size is Z1 we are getting error that factory calendar is not extended to 2016. After analysis understand that this is due to long planning horizan (350 days) defined for that plant and lot size as nine months. During MRP system calculating the total period as 350 days + Nine months. So in this case period is ovelapping in to fiscal year 2016, which is not defined.

Resolution


So advised client to extended the factory calendar to year 2016.